TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 08/22/2024
Notice Eff Time: 09:15:06 CDT
Notice End Date:
Notice End Time:
Notice ID: 14869963
Notice Stat Desc: Initiate
Notice Type Desc: Maint / Other
Post Date: 08/22/2024
Post Time: 09:15:06 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Station 35 Update - Unplanned Maintenance

Due to unexpected issues during the Station 35 planned maintenance (Job 48733), Transco needs to complete additional facility modifications that need to be performed before the compressor station is able to come back online. The current anticipated schedule for this unplanned work is August 23, 2024 through September 30, 2024 (“Unplanned Outage Period”).

Operating Conditions resulting from this unplanned work may require Transco to manage transportation services moving south to north through the location listed below. The total quantity available will be contingent on system conditions. Transactions moving north to south through this location will not be impacted. 

The location Throughput Section Boundaries (“TSB”) for station 35 at mainline milepost 327.27 S-N may be used to manage capacity availability during this unplanned work. If needed an updated Market and Production Area constraint notice will include the TSB and the available quantity of all transportation priorities during the Unplanned Outage Period.

TSB Name - Location

Location ID

Flow Direction

ML S35 S to N MP 327.27

9011644

South to North

If you have any questions, please contact your Transportation Services Representative.