TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/15/2024
Notice Eff Time: 11:13:40 CDT
Notice End Date:
Notice End Time:
Notice ID: 14471838
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/15/2024
Post Time: 11:13:40 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Station 80 (Job 185598) Planned Outage and Maintenance Summary

Transco will be performing necessary planned maintenance associated with Job #185598 on its 2024 Planned Outage and Maintenance Summary. This maintenance activity requires a compressor station outage and will impact the availability of transportation services.  The current schedule for this maintenance is May 6, 2024 through June 17, 2024. 

Operating Conditions resulting from this work will require Transco to manage transportation services moving south to north through the location listed below. The total quantity available will be contingent on system conditions during the maintenance period, but is anticipated to be limited to the quantity indicated below. Transactions moving north to south through this location will not be impacted. 

The receipt-based Throughput Section Boundary (TSB) at mainline milepost 740.50 (Station 80) will be used to manage capacity availability including any required changes to the expected total quantity available during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of  transportation services during the indicated period. 

TSB Name - Location 

Location ID 

Flow Direction 

Total Quantity Available (Mdt/d) 

Station 80 MP 740.50 

9012483 

South to North 

1,600 

If you have any questions, please contact your Transportation Services Representative.