TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 08/08/2014
Notice Eff Time: 09:00:00 CDT
Notice End Date:
Notice End Time:
Notice ID: 5947117
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 08/08/2014
Post Time: 07:59:00 CDT
Prior Notice: 5928152
Reqrd Rsp Desc: No response required
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Station 515 Unplanned Maintenance Update

The unplanned maintenance at Compressor Station 515 in Bear Creek, PA is expected to be completed by August 22, 2014.  Transco apologizes for any inconvenience that this outage has caused.  After the maintenance is completed, the availability of non-secondary reverse path (NSRP), secondary FT and interruptible (IT) transportation services from west to east through Station 515 and east to west through Station 517 will be dependent on utilization and system conditions.

As a reminder, the anomaly investigations associated with Job No. 54 on Transco’s 2014 Major Planned Maintenance and Outage Summary are currently planned for August 15, 2014 through August 22, 2014.

If you have any questions, please call your Transportation Services Representative.

Ross Sinclair

Manager, Pipeline Control