Gulfstream Natural Gas System L.L.C.
Critical: Y
Notice Eff Date: 08/29/2006
Notice Eff Time: 16:09:18 CDT
Notice End Date:
Notice End Time:
Notice ID: 1084499
Notice Stat Desc: Initiate
Notice Type Desc: Maintenance
Post Date: 08/29/2006
Post Time: 16:09:18 CDT
Prior Notice: 0
Reqrd Rsp Desc: No response required
Rsp Date:
Rsp Time:
TSP: 017738746
TSP Name: Gulfstream Natural Gas System L.L.C.

Notice Text:

Subject: Facility Outage Notice: Destin Receipt Point

August 29, 2006

Date: August 29, 2006

 

To: Gulfstream Natural Gas Customers and Shippers

 

Re: Facility Outage Notice: Destin Receipt Point

 

On May 25, 2006, Gulfstream posted a notice on its EBB informing all interested parties that Gulfstream was expanding the capacity of the existing receipt point interconnection between Gulfstream and Destin Pipeline Company located in Pascagoula, Mississippi to increase the nominal design capacity of the Destin interconnect to 1,000 Mdt/d. The May 25, 2006 notice also indicated that a brief outage would be required to make the final tie-ins for the expanded interconnect.

 

Gulfstream is currently constructing the expansion of the Destin interconnect. At this time, Gulfstream plans to complete the final tie-ins at the Destin interconnect during the period from 9:00 a.m. CT on October 5, 2006 through 9:00 a.m. CT on October 9, 2006, during which period the Destin receipt point will not be available for receipts into the Gulfstream system. The expanded Destin receipt point is scheduled to be placed into service at 9:00 a.m. CT on October 9, 2006. Gulfstream will update this posting if this schedule changes.

 

Please call your Marketing Account Representative if you have any questions about this posting or the outage.

 

Terry C. Fitch

Manager Operations Control