TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 10/25/2022
Notice Eff Time: 09:00:00 CDT
Notice End Date: 11/01/2022
Notice End Time: 09:00:00 CDT
Notice ID: 13010195
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 10/06/2022
Post Time: 11:36:41 CDT
Prior Notice: 0
Reqrd Rsp Desc: No response required
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job #450 2022 Planned Outage and Maintenance Summary

Transco’s Job #450, as referenced in Transco’s Planned Outage and Maintenance Summary is currently scheduled to begin on October 25, 2022, and last through October 31, 2022.

During this period, Station 54 and associated Washington storage will not be available. Services under all WSS rate schedules may not be available for the period October 25 through October 31, 2022, due to Operating Conditions resulting from this planned equipment outage. Transco requests all WSS storage customers not to provide any quantities for injection under any WSS rate schedule during this period.

If Transco is required to restrict WSS services, including injections under any WSS rate schedule, additional notice will be provided.

Additionally, this work will reduce Transco’s ability to manage system imbalances and recommends shippers maintain a concurrent balance of receipts and deliveries daily.

If you have any questions, please contact your Commercial representative.