TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 05/17/2022
Notice Eff Time: 00:00:00 CDT
Notice End Date: 05/26/2022
Notice End Time: 00:00:00 CDT
Notice ID: 12654447
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 05/26/2022
Post Time: 08:35:49 CDT
Prior Notice: 12423238
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Update - Job # 233 Planned Outage and Maintenance Summary

Transco has provided notice of planned construction activity associated with Job #233 on its 2022 Planned Outage and Maintenance Summary.  This planned maintenance will require an outage on the 24” Leidy Line “A” from May 17 through May 26, 2022.

During this outage, the total scheduled quantity available at the Leidy Line Aggregate Receipt MP 101 location, 1Line Location ID 9007682 will be 1,000,000 Dth/d.  If required, the individual locations that make-up this constrained segment of the pipeline will be allocated a portion of the available capacity based on the priority of the transactions requesting service through this segment.

As this work progresses, Transco will continue to evaluate system conditions and may adjust the available quantities at the Leidy Line Aggregate Receipt MP 101 location as system conditions dictate. A separate “Market and Production Constraints” notice will be posted indicating the total quantity available at this location.

TSB Name - Location

Location ID

Leidy Line Aggregate Receipt MP 101

9007682

If you have any questions, please contact your Commercial Services Representative.