TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 02/01/2022
Notice Eff Time: 09:53:12 CST
Notice End Date: 03/31/2022
Notice End Time: 01:00:00 CDT
Notice ID: 12361318
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 02/01/2022
Post Time: 09:53:12 CST
Prior Notice: 12323948
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Upcoming Gulfstream Phase VI Project Outage Timeframe Update

Transco has been notified of Gulfstream Natural Gas System, L.L.C.’s  (“Gulfstream”) updated outage posting in connection with its Phase VI Project whereby Gulfstream anticipates the potential for a construction-related system outage(s) to occur in March of 2022 (estimating up to 14 days).  Gulfstream will be initiating discussions with its shippers and connected point operators related to the scheduling of that outage(s).

During the proposed Gulfstream Phase VI outage, receipts of gas in Mississippi and Alabama will be unavailable and Transco will be unable to make deliveries to Coden (location 9003000) during that time.

The Gulfstream locations affected are:

Gulfstream Coden (9002960)

Williams Mobile Bay plant (8205171)

DCP Mobile Bay (82051791)

Destin Pascagoula (8205175)

Gulf South Bayou Jonas (8205177)

Southeast Supply Header (9004282)