TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 01/12/2022
Notice Eff Time: 08:10:02 CST
Notice End Date:
Notice End Time:
Notice ID: 12299610
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 01/12/2022
Post Time: 08:10:02 CST
Prior Notice: 12285224
Reqrd Rsp Desc: No response required
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Update: Job #249 Planned Outage and Maintenance Summary

Transco’s Job #249, as referenced in Transco’s Planned Outage and Maintenance Summary, is currently scheduled to begin January 19, 2022 with a planned completion on January 25, 2022 (“System Outage Period”).

During the System Outage Period, the locations listed below will not be available for scheduling or flow. 

Location ID

Location Name

 Flow Direction

9012023

Edna M3673

Receipt

9002900

Cameron Interstate Pipeline

Bi-Directional

1006218

Ragley-Trunkline

Receipt

If you have any questions, please contact your Commercial Representative.