TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 11/22/2021
Notice Eff Time: 00:00:00 CST
Notice End Date: 11/23/2021
Notice End Time: 00:00:00 CST
Notice ID: 12130899
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 11/09/2021
Post Time: 09:34:14 CST
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job #524 Planned Outage and Maintenance Summary

Transco has provided notice of planned construction activity associated with Job #524 on its 2021 Planned Outage and Maintenance Summary. This planned maintenance will require a one day outage at the Compressor Station 190 facility. The current schedule requires the existing compression facility to be out of service on November 22, 2021.

During this period of construction, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving north to south through station 190 will not be available.

Operating Conditions resulting from this work may also require Transco to restrict primary firm gas transportation services moving north to south through station 190. The actual volume impacted, if any, will be contingent on utilization during this period and communicated through an updated Market and Production Area constraint notice prior to the curtailment. Transactions moving south to north through station 190 are not expected to be impacted.

A receipt-based Throughput Section Boundary (TSB) at mainline milepost 1628.78 (Station 190) will be used to manage capacity during this planned work.

TSB Name - Location

Location ID

Flow Direction

Compressor Station 190 MP 1628.78

9011620

North to South

 

If you have any questions, please contact your Commercial Services Representative.