TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 07/20/2021
Notice Eff Time: 08:51:36 CDT
Notice End Date:
Notice End Time:
Notice ID: 11849403
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 07/20/2021
Post Time: 08:51:36 CDT
Prior Notice: 11775433
Reqrd Rsp Desc: No response required
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Update: Job #353 Planned Outage and Maintenance Summary

Transco’s Job #353, as referenced in Transco’s Planned Outage and Maintenance Summary is currently scheduled to begin July 6, 2021, with a planned completion on July 22, 2021.

This planned maintenance will require segment(s) of the Southeast Louisiana Lateral (SELA) to be isolated from the remainder of the SELA system. The locations listed below will not be available for scheduling or flow during this outage period.

Location ID

Location Name

Meter

Flow Direction

1006531

Livingston

4398

Delivery

1006267

ST. Helena

4305

Delivery

If you have any questions, please contact your Commercial Representative.