TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 03/01/2022
Notice Eff Time: 00:00:00 CST
Notice End Date: 03/11/2022
Notice End Time: 00:00:00 CST
Notice ID: 11823059
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 07/07/2021
Post Time: 16:22:35 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Upcoming Gulfstream Phase VI Project Outage Timeframe

Transco has been notified of Gulfstream Natural Gas System, L.L.C.’s outage that will result in receipts of gas in Mississippi and Alabama being unavailable March 1-11, 2022.  Transco will be unable to make deliveries to Coden (location 9003000) at this time.

 

The Gulfstream locations affected are:

Gulfstream Coden (9002960)

Williams Mobile Bay plant (8205171)

DCP Mobile Bay (82051791)

Destin Pascagoula (8205175)

Gulf South Bayou Jonas (8205177)

Southeast Supply Header (9004282)